Estimated Time of Completion, or ETC, is the metric that tells you how much more work you have to do to finish a project. It is one of the cornerstones of earned value management and one of the most useful numbers a PM can compute in five minutes a week.

Despite that, most A&E firms do not use ETC formally. They estimate remaining work informally, or not at all. This guide fixes that.

Engineer reviewing project completion estimate

What ETC actually means

ETC is the forecast amount of effort, in hours or dollars, still required to complete the remaining work on a project. It is not the same as Estimate at Completion, which is the total project forecast.

  • BAC (Budget at Completion): the original total budget.
  • AC (Actual Cost): what has been spent so far.
  • ETC (Estimate to Complete): what we forecast it will take to finish from here.
  • EAC (Estimate at Completion): AC plus ETC. The total forecast.

ETC is the forward looking number. Done well, it tells you whether the project is going to overrun before the overrun happens.

Step 1: Capture actuals to date

The starting point is what you have already used. Pull total hours logged by phase and total fee burned. The data should come straight from your time tracker without manual aggregation.

If your data is stale, ETC is fiction. Daily time entry is a prerequisite.

Step 2: Calculate percent complete by phase

For each active phase, the PM estimates what percent of the work is actually finished. Not what percent of the budget has been burned. The percent of physical completion.

This is the human judgment step. The PM walks the deliverables and rates each one as done, in progress, or not started. Average the ratings to get phase completion.

This is also the step where most ETC calculations go wrong. The temptation is to use percent burn as a proxy for percent complete. Resist it. They are different numbers and the gap between them is the early warning signal.

Step 3: Apply one of three ETC formulas

There are three standard ETC formulas. Each fits a different project situation.

Formula A: ETC equals BAC minus EV

EV (Earned Value) is the budget for the work that is actually complete. ETC = BAC − EV.

Use when: the project is on track and you have no reason to believe future productivity will differ from the original plan. Rare in practice.

Formula B: ETC equals (BAC minus EV) divided by CPI

CPI (Cost Performance Index) is EV divided by AC. It tells you how efficient the work has been so far.

Use when: past efficiency is the best predictor of future efficiency. The most common formula in A&E projects.

Formula C: Bottom up re estimate

The PM walks the remaining work and estimates each task individually. The most accurate but most time consuming option.

Use when: the project has changed materially from the original plan, or when scope creep has rendered the original budget meaningless.

ETC calculation on a project dashboard

Step 4: Compare ETC against budget remaining

Now you have a forecast for what remains. Compare it to what is left in the budget for those remaining phases.

The arithmetic.

  • Budget remaining = BAC − AC.
  • Variance = Budget remaining − ETC.
  • Negative variance = forecast overrun.
  • Positive variance = forecast underrun.

A 5 percent overrun forecast is normal noise. A 15 percent overrun forecast is a partner conversation. A 25 percent overrun forecast is a change order conversation with the client.

Step 5: Communicate the result and act

ETC is only useful if it changes behavior. The PM brings the ETC and variance to the weekly burn meeting. The team makes a decision.

Three typical responses to a forecast overrun.

  1. Reduce remaining scope. Negotiate with the client to drop a deliverable or simplify a phase.
  2. Add capacity. Bring in another team member to compress remaining time.
  3. Initiate a change order. If the overrun is driven by added scope, capture it formally.

Without ETC, none of these decisions happen until the budget is already blown.

A worked example

A 250,000 dollar project, halfway through.

  • BAC: 250,000.
  • AC (spent so far): 145,000.
  • EV (budget for work complete): 125,000 (50 percent done).
  • CPI: 125,000 / 145,000 = 0.86.

Apply Formula B.

ETC = (BAC − EV) / CPI = (250,000 − 125,000) / 0.86 = 145,348.

EAC = AC + ETC = 145,000 + 145,348 = 290,348.

Forecast overrun: 290,348 − 250,000 = 40,348, or about 16 percent over budget at completion.

That is a partner level conversation this week. Not a panic, but a clear signal that the second half of the project needs different management than the first half.

The five common mistakes

  • Using percent burn as percent complete. Different numbers. The gap is your warning.
  • Updating ETC monthly instead of weekly. By month end the conversation is too late.
  • Ignoring the formula choice. Formula A is rarely right in real A&E projects.
  • Not communicating the variance. A forecast overrun in the PM's notebook does not change behavior.
  • Treating ETC as math instead of judgment. The numbers are an input. The PM's read of the remaining work is what matters.

How ETC fits with BAC and other earned value metrics

ETC is one piece of the earned value management toolkit. BAC is the original budget. AC is what has been spent. EV is the budget for what has been done. Together with CPI and SPI (Schedule Performance Index), these metrics let you talk about project health quantitatively instead of impressionistically.

Most A&E firms run on impressions. The ones that move to quantitative project tracking outperform their peers on margin.

The 30 day starting plan

Pick one active project. Set up the BAC, AC, EV tracking. Calculate ETC weekly using Formula B for four weeks. Watch the variance trend.

By week four, the PM has a working model and is making decisions on data. Roll it to a second project. By month three, ETC is a habit, not a special exercise.

ETCearned valueproject trackingBACEACCPI
C

Costifys Editorial

Project Finance

Contributing writer at Costifys, helping architecture and engineering firm leaders make better decisions about practice management, financial performance, and operational efficiency.

Track every dollar with real-time budget dashboards

See budget vs. actuals by phase, flag overruns before they happen, and keep every project profitable.

Get weekly A&E firm insights

Budgeting tips, utilization benchmarks, and product updates. No spam.